Engineers propose short-term fix for Skagway rockslides, assembly moves it forward | KHNS Radio | KHNS FM

2022-10-16 09:21:32 By : Ms. Tracy Lei

Posted by Mike Swasey | Oct 8, 2022 | Featured Stories, News | 0

A rockslide on September 24 wiped out WPYR’s attenuator net on Skagway’s Railroad Dock. (Photo courtesy Andrew Cremata)

Skagway’s busiest cruise ship dock was barraged by rockslides during the 2022 cruise season creating partial shutdowns of the dock and resulting in a loss of well over one hundred thousand visitors to the community. The vast majority of the town’s economy relies on cruise ship traffic. As KHNS’ Mike Swasey reports, in an effort to reduce the hazard moving forward, the municipality has contracted with a design firm to develop mitigation strategies that could allow at least partial use of the dock next season.

Seattle-based Geotechnical Engineering firm Shannon and Wilson have developed two different mitigation proposals for Skagway’s large rockslide chute officials are calling the South Slide area. It’s located above the north end of the Railroad Dock and clearly visible from the waterfront. 

The two plans consist of a large-scale long-term effort costing nearly $40 million, and a smaller short-term effort that would cost a little over $3 milliion. The municipality is seeking grant funding for the long-term project but is moving ahead with the short-term project in the meantime.

Municipal officials hope that the short-term project can be done prior to next year’s cruise season. That project will include the installation of two attenuator nets. One of those, at the bottom of the slide area, was destroyed during a slide late last month, it was the large netting designed to guide falling rocks into the water below the dock. It will need to be replaced.

Another attenuator net will be installed in the mid-slope area. During Thursday’s assembly meeting, Borough Manager Brad Ryan explained why that’s necessary.

“I’d say a third of the way down or maybe just over a third of the way down, there’s a bump on the hillside, and that kicks rocks off and launches them outward,” said Ryan.

When those rocks get launched outward, they can gain speed and miss the attenuator net at the bottom of the slope causing damage to the dock below. The plan also calls for a draped mesh at the top of the slope much like what is used along stretches of the South Klondike Highway between Skagway and Carcross in Canada’s Yukon Territory. The concept is that if you can slow the speed at which the rocks fall, the impact won’t be as damaging.

Heavy scaling will also be done to the top of the slide area. That will theoretically bring down any loose rock or vegetation that’s in danger of falling now. The scaling will be done with hand tools such as pry bars and airbags. 

But Ryan doesn’t expect that the Railroad Dock will be used at full capacity upon completion of the mitigation effort.

“I think we have to be prepared that we’re going to try to limit as many people on that dock as possible,” said Ryan.

That means most likely cruise passengers will continue to be tendered from the ships that are able to berth on the Railroad Dock south of the slide area next season.

Ryan said funding for the project will likely come from a variety of sources. Alaska Governor Mike Dunleavy declared a Disaster Emergency in Skagway last month and the state made at least $1 million available for Skagway in the wake of the declaration. There could be more funds available but those aren’t guaranteed.

Another potential source of funding could come from CPV funds which are collected by the State of Alaska as a per-passenger fee and then distributed back to communities that host cruise ships. 

“Can we cover it? I believe we can. The revenue bond has to go through and the expenses that would go to the development of the (Ore) dock would have to all go through that revenue bond, which we intend to do anyway. And then we’d have to cover it with our other municipal funds,” said Ryan.

$65 million revenue bond was approved by voters on Tuesday. Those funds are supposed to be used for port development and are expected to be available early next year. The use of that money to reconfigure the Ore Dock to allow large-class cruise ships next year would allow other money, like those CPV funds, to be available to help pay for the rockslide mitigation plan instead of the emergency Ore Dock redesign project.

Shannon and Wilson expect two weeks for the hand scaling, eight weeks for attenuator construction, and one week to test the system. Oregon-based contractor Rock Supremacy was named by Manager Ryan as the contractor that will execute the plan. White Pass and Yukon Route will continue to share geotechnical data and remove debris from the bottom of the slide area as needed.

Your email address will not be published. Required fields are marked *

Serving Haines, Skagway and Klukwan on 102.3 and 91.9 FM

LOCATION Chilkat Center for the Arts One Theatre Dr, Haines, AK 99827

MAILING ADDRESS P.O. Box 1109, Haines, AK 99827

TELEPHONE 907-766-2020 in Haines 907-983-2853 in Skagway

EMAIL Contact us via email